Dundee Precious Metals EAD 76 – CEMENTED PASTE BACKFILL PLANT – Electrical and Instrumentation Installation 2010
Dundee Precious Metals EAD Concentrator Upgrade Project – 13 Grinding – SAG Mill –

 

E&I Installation 2010-2011
Dundee Precious Metals EAD Area 27– Project: Underground Crusher and Conveying

System

Electrical Equipment & Instrumentation Installation 2012 г.
Dundee Precious Metals EAD AREA 78 – Lighting Installation of TMF Walls Electrical works – building lighting installation for TMF Walls Start: 09.2013

End: 12.2013

AURUBIS Bulgaria EAD IN.149 – Treatment Plant Rain Water, Area 970 Electrical works  (electrical, I & C) building transformer substation 6 / 0,4kV, cable routing and power lines.

Building earthing, and lighting installation.
Commissioning, electrical мeasurements with the issuance of reports by an accredited laboratory.

Start: 11.2013 End: 05.2014
AURUBIS Bulgaria EAD IU.170 – Filter press, flotation plant Electrical works  (electrical, I & C)

Building earthing and lighting installation.

Start: 02.2014г. End: 03.2014г.
AURUBIS Bulgaria EAD ПД №Р80/22006739 “Garage for fire truck to an existing building”, located on the industrial site of AURUBIS Bulgaria EAD Electrical works  (electrical)

Building earthing, lightning and lighting installation. Commissioning, electrical мeasurements with the issuance of reports by an accredited laboratory.

Begin: 08.2014 End: 08.2014
Dundee Precious Metals EAD AREA 14 – Electrical and Instrumentation Installation –

MULTISTREAM ANALYZER PROJECT

Electrical works  (electrical, I & C)cable routing and power lines.
Commissioning, electrical  measurements with the issuance of reports by an accredited laboratory.
Start: 09.2014 End: 08.2014
Dundee Precious Metals EAD Dismantling of old cables and laying of new ones 6 kV through Kapitalna Shaft Construction of cable routes and power lines 6kV, installation and connection. Measurements with the issuance of reports by an accredited laboratory. Start: 07.2014 End: 08.2014
Dundee Precious Metals EAD AREA 18 – Electrical and Instrumentation Installation –

PYRITE HANDLING PROJECT  Stage 1

Electrical works  (electrical, I & C)cable routing and power lines.
Commissioning, electrical measurements with the issuance of reports by an accredited laboratory.Building earthing and lighting installation.
Start: 03.2014 End: 06.2014
Dundee Precious Metals EAD Electrical and Instrumentation Installation –

PYRITE HANDLING PROJECT. Stage 2,3

Electrical works  (electrical, I & C)cable routing and power lines.
Measurements with the issuance of reports by an accredited laboratory.Building earthing and lighting installation.
Start: 04.2015 End: 06.2015
Dundee Precious Metals EAD Electrical installation of dust suppressing system Electrical works  (electrical, I & C)cable routing and power lines. Start: 07.2015 End: 07.2015
Dundee Precious Metals EAD Reconstruction of electrical installation in building “Mine
administration”
Electrical works  (Еlectrical)cable routing. Building system Start: 06.2015 End: 08.2015
AURUBIS Bulgaria EAD project IN.143.31 – Electrical works middle hopper batch. Electrical works  (electrical, I & C)cable routing and power lines.
Measurements with the issuance of reports by an accredited laboratory.Building earthing and lighting installation.
Start: 09.2015 End: 10.2015
AURUBIS Bulgaria EAD Reconstruction II System plant for  H2SO4 – Converter Electrical works  (electrical, I & C)cable routing and power lines  6kV,0.4kV  – installation and connection

Building earthing and lighting installation.

Start: 04.2016 End: 05.2016
ТРЕЙС – СОФИЯ ЕАД Building a landfill sludge from wastewater treatment and emissions – AURUBIS Bulgaria EAD Electrical works  (electrical, I & C)cable routing and power lines.
Measurements with the issuance of reports by an accredited laboratory.Building earthing and lighting installation.
Start: 04.2016 End: 06.2016
AURUBIS Bulgaria EAD Retrofitting substations:  TP 201/1, TP 201/2 and TP 201/3, Area 100 Electrical works  (electrical). Disconnecting, phasing, all cables of existing sections, dismantling the electrical boards, installation of new switchboards and sections,  0,4kV. Measurements and Commissioning of the equipment. Construction of cable routes Start: 05.2016 End: 07.2016
AURUBIS Bulgaria EAD Retrofitting substations:  ТP 202/4 – Electrical works Electrical works  (electrical). Disconnecting, phasing, all cables of existing sections, dismantling the electrical boards, installation of new switchboards and sections,  0,4kV. Measurements and Commissioning of the equipment. Construction of cable routes Start: 02.2016 End: 03.2016