| Company Name | Project Name | Work Provided | Year |
| Dundee Precious Metals EAD | 76 – CEMENTED PASTE BACKFILL PLANT – | Electrical and Instrumentation Installation | 2010 |
| Dundee Precious Metals EAD | Concentrator Upgrade Project – 13 Grinding – SAG Mill –
|
E&I Installation | 2010-2011 |
| Dundee Precious Metals EAD | Area 27– Project: Underground Crusher and Conveying
System |
Electrical Equipment & Instrumentation Installation | 2012 г. |
| Dundee Precious Metals EAD | AREA 78 – Lighting Installation of TMF Walls | Electrical works – building lighting installation for TMF Walls | Start: 09.2013
End: 12.2013 |
| AURUBIS Bulgaria EAD | IN.149 – Treatment Plant Rain Water, Area 970 | Electrical works (electrical, I & C) building transformer substation 6 / 0,4kV, cable routing and power lines.
Building earthing, and lighting installation. |
Start: 11.2013 End: 05.2014 |
| AURUBIS Bulgaria EAD | IU.170 – Filter press, flotation plant | Electrical works (electrical, I & C)
Building earthing and lighting installation. |
Start: 02.2014г. End: 03.2014г. |
| AURUBIS Bulgaria EAD | ПД №Р80/22006739 “Garage for fire truck to an existing building”, located on the industrial site of AURUBIS Bulgaria EAD | Electrical works (electrical)
Building earthing, lightning and lighting installation. Commissioning, electrical мeasurements with the issuance of reports by an accredited laboratory. |
Begin: 08.2014 End: 08.2014 |
| Dundee Precious Metals EAD | AREA 14 – Electrical and Instrumentation Installation –
MULTISTREAM ANALYZER PROJECT |
Electrical works (electrical, I & C)cable routing and power lines. Commissioning, electrical measurements with the issuance of reports by an accredited laboratory. |
Start: 09.2014 End: 08.2014 |
| Dundee Precious Metals EAD | Dismantling of old cables and laying of new ones 6 kV through Kapitalna Shaft | Construction of cable routes and power lines 6kV, installation and connection. Measurements with the issuance of reports by an accredited laboratory. | Start: 07.2014 End: 08.2014 |
| Dundee Precious Metals EAD | AREA 18 – Electrical and Instrumentation Installation –
PYRITE HANDLING PROJECT Stage 1 |
Electrical works (electrical, I & C)cable routing and power lines. Commissioning, electrical measurements with the issuance of reports by an accredited laboratory.Building earthing and lighting installation. |
Start: 03.2014 End: 06.2014 |
| Dundee Precious Metals EAD | Electrical and Instrumentation Installation –
PYRITE HANDLING PROJECT. Stage 2,3 |
Electrical works (electrical, I & C)cable routing and power lines. Measurements with the issuance of reports by an accredited laboratory.Building earthing and lighting installation. |
Start: 04.2015 End: 06.2015 |
| Dundee Precious Metals EAD | Electrical installation of dust suppressing system | Electrical works (electrical, I & C)cable routing and power lines. | Start: 07.2015 End: 07.2015 |
| Dundee Precious Metals EAD | Reconstruction of electrical installation in building “Mine administration” |
Electrical works (Еlectrical)cable routing. Building system | Start: 06.2015 End: 08.2015 |
| AURUBIS Bulgaria EAD | project IN.143.31 – Electrical works middle hopper batch. | Electrical works (electrical, I & C)cable routing and power lines. Measurements with the issuance of reports by an accredited laboratory.Building earthing and lighting installation. |
Start: 09.2015 End: 10.2015 |
| AURUBIS Bulgaria EAD | Reconstruction II System plant for H2SO4 – Converter | Electrical works (electrical, I & C)cable routing and power lines 6kV,0.4kV – installation and connection
Building earthing and lighting installation. |
Start: 04.2016 End: 05.2016 |
| ТРЕЙС – СОФИЯ ЕАД | Building a landfill sludge from wastewater treatment and emissions – AURUBIS Bulgaria EAD | Electrical works (electrical, I & C)cable routing and power lines. Measurements with the issuance of reports by an accredited laboratory.Building earthing and lighting installation. |
Start: 04.2016 End: 06.2016 |
| AURUBIS Bulgaria EAD | Retrofitting substations: TP 201/1, TP 201/2 and TP 201/3, Area 100 | Electrical works (electrical). Disconnecting, phasing, all cables of existing sections, dismantling the electrical boards, installation of new switchboards and sections, 0,4kV. Measurements and Commissioning of the equipment. Construction of cable routes | Start: 05.2016 End: 07.2016 |
| AURUBIS Bulgaria EAD | Retrofitting substations: ТP 202/4 – Electrical works | Electrical works (electrical). Disconnecting, phasing, all cables of existing sections, dismantling the electrical boards, installation of new switchboards and sections, 0,4kV. Measurements and Commissioning of the equipment. Construction of cable routes | Start: 02.2016 End: 03.2016 |